Tanks Ready for Inspection and Sealing!

I went by the EAA tool crib today and got a flare tool so I could finish the vent lines and get the final half of the inboard ribs installed. Luckily that went off without a hitch and the tanks are now ready to be inspected! I called my wonderful Read more…

By olanandkate, 7 hoursJune 21, 2025 ago
Fuel System

Left Tank J Stiffener and Both Forward Brackets Done

I got a little bit of time today to finish the J stiffener and I got both of the forward mount brackets done too. I now need to let that sit and work on getting the fuel vent lines installed. I’ll get to try out my latest tool for bending Read more…

By olanandkate, 1 dayJune 20, 2025 ago
Fuel System

Right Tank J Stiffener Installed

Took a bit to figure out how best to tackle this but I got it done. The longest part was going back and capping over the rivets and getting the underside of the J stiffener sealed up. I think the next one I do I am going to put a Read more…

By olanandkate, 2 daysJune 19, 2025 ago
Fuel System

All Tank Ribs Installed

I got the rest of the 6 ribs installed today. It took me about 45 minutes each between cleaning, mixing, riveting, etc. Glad this is over with and I can move on to the other things like the J channel and bracket installs tomorrow.

By olanandkate, 3 daysJune 18, 2025 ago
Fuel System

More Tank Ribs Installed

I didn’t get alot of time today as I was busy with work, school (grading), or church stuff. But I did get four ribs installed. Good progress and trying to keep it as neat and tidy as possible.

By olanandkate, 4 daysJune 17, 2025 ago
Fuel System

Shims & First Full Ribs Complete

I got the shims in while we were at Lake Texoma. I got those trimmed and installed. I then got the first two full ribs installed in each tank. I’ve been watching some people on how they keep their installs so clean and they talk about keeping a clean workstation Read more…

By olanandkate, 5 daysJune 16, 2025 ago
Fuel System

Inboard Forward Ribs Installed

Well I did end up having a little bit of time today before Kate got home to do some work. I got the forward inboard ribs installed because they would be fairly easy with the squeezer and not having to have sealant over the entire rib flange. I double checked Read more…

By olanandkate, 1 weekJune 13, 2025 ago
Fuel System

All Stiffeners Installed

Another day that I didn’t get much time to work on the plane as we are prepping to go to my mom’s this weekend and I also needed to do some automotive maintenance on my wife’s car as well as the boys. But I got all of the stiffeners installed Read more…

By olanandkate, 1 weekJune 12, 2025 ago
Fuel System

Right Tank Stiffeners Halfway Complete

I didn’t get nearly as much time as I wanted tonight as I had church duties that came up and took two hours of my time away, but I’m still happy with my progress. I hope to wrap the rest of these stiffeners up tomorrow.

By olanandkate, 1 weekJune 11, 2025 ago
Fuel System

Left Tank Stiffeners Complete

I got a little bit of time to work tonight and finished up the left wing tank stiffeners. Not much else to report besides that.

By olanandkate, 2 weeksJune 10, 2025 ago

Posts pagination

1 2 3 Next

Aircraft Build Time

Airplane sectionBuild time (hrs)
S06 - Vertical Stabilizer22.5
S07 - Rudder34.25
S08 - Horizontal Stabilizer49.75
S09 - Elevators59
S10 - Tailcone75.75
S11 - Empennage Attach27.75
S12 - Empennage Fairings26.5
S13 - Main Spar18.25
S14 - Wing Ribs35.5
S15 - Rear Spar29.25
S16 - Top Skins32.75
S17 - Outboard Leading Edge34.75
S18 - Fuel Tank52
S21 - Aileron35
Total533
Recent Posts
  • Tanks Ready for Inspection and Sealing!
  • Left Tank J Stiffener and Both Forward Brackets Done
  • Right Tank J Stiffener Installed
  • All Tank Ribs Installed
  • More Tank Ribs Installed
Recent Comments
    Archives
    • June 2025
    • May 2025
    • April 2025
    • February 2025
    • January 2025
    • December 2024
    • October 2024
    • September 2024
    • August 2024
    • July 2024
    • September 2023
    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • January 2023
    • December 2022
    • September 2022
    • August 2022
    • April 2022
    • March 2022
    • December 2021
    • November 2021
    • June 2021
    • May 2021
    • April 2021
    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • July 2020
    • June 2020
    • May 2020
    Categories
    • Costs
    • Empennage
    • Fuel System
    • Research
    • Tools
    • Travel
    • Uncategorized
    • Wings
    • Workshop
    Hestia | Developed by ThemeIsle