S38 - Rudder Pedals & Brake System

Fuselage

Rudder Cable Linkages Complete

Wrapping up this section for now and I will come back to it at a later date. I fabricated all four of the rudder cable linkages and got them installed. I will need to remove them later when I have a bunch of parts to prime so I can prime Read more

By olanandkate, 1 monthSeptember 1, 2025 ago
Fuselage

Brake Lines Finished and Rudder Wire Guides Installed

I installed the steel braided lines which wasn’t too difficult since it is basically just screwing on both ends. The flexible lines were a bit more of a pain. The brass ferrules that needed to be installed in the ends of the lines were pretty difficult. I tried boiling the Read more

By olanandkate, 1 monthAugust 31, 2025 ago
Fuselage

Rudder Pedals Installed and Rudder Cables Ran

Ok, I ended up having more time than I expected. By the time we got to the game we were only 20ish minutes away from kickoff and parking was now way too far away so I dropped the family off and went home. I ran the rudder cables while I Read more

By olanandkate, 1 monthAugust 30, 2025 ago
Fuselage

Rudder Pedals Assembled

I didn’t get a ton of time today as I have a baptism that I get to attend and then my son is playing in the OU band tonight for their high school recruitment night so I got as much as I could done. I got the pedals assembled, installed, Read more

By olanandkate, 2 monthsAugust 30, 2025 ago
Fuselage

Rudder Pedals Cut, Deburred, and Primed

While I’m still waiting to decide on what fuel system I want to use, I went ahead and started section 37 which is the installation of the rudder pedals, brake cylinders, and rudder cabling. So the title pretty much wraps up the total time I’m counting in this post for Read more

By olanandkate, 2 monthsAugust 29, 2025 ago

Aircraft Build Time

Airplane sectionBuild time (hrs)
Avionics/Electronics9
S06 - Vertical Stabilizer22.5
S07 - Rudder34.25
S08 - Horizontal Stabilizer49.75
S09 - Elevators59
S10 - Tailcone75.75
S11 - Empennage Attach27.75
S12 - Empennage Fairings26.5
S13 - Main Spar18.25
S14 - Wing Ribs35.5
S15 - Rear Spar29.25
S16 - Top Skins32.75
S17 - Outboard Leading Edge34.75
S18 - Fuel Tank79.5
S20 - Bottom Skins42.25
S21 - Aileron35.5
S22 - Flap44
S23 - Aileron Actuation11
S24 - Wing Tip Installation15.5
S25 - Mid Fuselage Bulkheads0.25
S26 - Mid Fuselage Ribs Bottom Skins0.25
S27 - Firewall0.25
S28 - Forward Fuselage Bulkhead Ribs0.25
S29 - Fuselage Side Skins4
S30 - Step Installation2
S31 - Upper Forward Fuselage0.25
S32 - Tailcone Attach14.75
S33 - Baggage Area28
S34 - Baggage Door8
S35 - Access & Floors7.75
S36 - Brake Lines4.5
S37 - Fuel System5.75
S38 - Rudder Pedals & Brake System12.5
S39 - Control System8.75
S40 - Flap System5
S42 - Rear Seat Backs7.5
S49 - Seats9
S50 - Cabin Heat1
Total802.5
Recent Posts
  • Control Column Bolted and Control Sticks Measured
  • Controls Installed
  • Front Seats Complete!
  • Seat Track Slides & Recline Housings Attached
  • Seat Pans Riveted & Bolted
Recent Comments
    Archives
    • October 2025
    • September 2025
    • August 2025
    • July 2025
    • June 2025
    • May 2025
    • April 2025
    • February 2025
    • January 2025
    • December 2024
    • October 2024
    • September 2024
    • August 2024
    • July 2024
    • September 2023
    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • January 2023
    • December 2022
    • September 2022
    • August 2022
    • April 2022
    • March 2022
    • December 2021
    • November 2021
    • June 2021
    • May 2021
    • April 2021
    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • July 2020
    • June 2020
    • May 2020
    Categories
    • Avionics
    • Controls
    • Costs
    • Empennage
    • Fuel System
    • Fuselage
    • Research
    • Tools
    • Travel
    • Uncategorized
    • Wings
    • Workshop
    Hestia | Developed by ThemeIsle